HighOpenD-09 · FinancialOwner: District Collector cell

Funds released and idle for 302 days

Lift irrigation pump · Palakkad, Kerala · sanctioned 24 Mar 2025 · detected 06 Jan 2026 (61 days ago)

Why this was flagged

score 79 / 100

Rule engine + ageing buckets evaluated this work against 734 comparable sanctions in Kerala for the same category and financial year. Money released to the implementing agency but unspent past the scheme's holding window, with no revised work programme on record. The residual for this record falls outside the learned tolerance, and the contribution breakdown below isolates which measured features carried the score.

Composite score
79
Model confidence
0.77
Peer cohort
747 works
Tier
High ≥ 66
Feature contribution to the score
  1. 01Days funds held unspent+30.5
  2. 02Unspent balance with the agency+19.0
  3. 03Revised work programme on record+14.7
  4. 04Interest credited to scheme account+8.9
  5. 05Utilisation certificate status+6.0

Contributions are additive against the cohort baseline; they sum to the composite score and are recomputed whenever the underlying record changes.

Evidence

drawn from the source records
Unspent balanceRs 28.85 L
Utilisation certificateNot filed
SanctionedRs 32.03 L
ReleasedRs 29.31 L
ExpenditureRs 0.46 L
Physical progress9%

Record trail

  1. 24 Mar 2025Work sanctioned by the District Authority₹32.03 L · Palakkad Public Works Department
  2. 24 Mar 2025First instalment released to the implementing agency₹14.65 L
  3. 06 Jan 2026D-09 fired during the nightly scoring runRule engine + ageing buckets · confidence 0.77
  4. 06 Jan 2026Alert routed to District Collector cellResponse window 15 days

The work

MPLADS/KL/2544
Asset
Lift irrigation pump
Category
Minor irrigation
Recommended by
H. Sarkar · Rajya Sabha
Constituency
Palakkad 3
Implementing agency
Palakkad Public Works Department
Contractor
Chambal Associates
Status
Stalled
Beneficiaries
2,755
Money
Sanctioned32.03 L
Released29.31 L
Expenditure0.46 L
Unspent with agency28.85 L
Physical progress9%

Detector

D-09

Idle funds beyond permissible period

Money released to the implementing agency but unspent past the scheme's holding window, with no revised work programme on record.