Unit rate for passenger amenities sits in the district's top percentile
Bus passenger shelter · Gorakhpur, Uttar Pradesh · sanctioned 14 Feb 2024 · detected 15 Jan 2026 (70 days ago)
Why this was flagged
Robust z-score on peer cohort evaluated this work against 438 comparable sanctions in Uttar Pradesh for the same category and financial year. Per-unit cost of an asset sits in the upper tail of comparable works in the same district and quarter after size normalisation. The residual for this record falls outside the learned tolerance, and the contribution breakdown below isolates which measured features carried the score.
- 01Unit rate vs district SoR+33.1
- 02Peer-cohort robust z-score+16.8
- 03Quantity declared per lakh+9.3
- 04Material index adjustment+7.3
- 05Quarter-on-quarter rate drift+5.6
Contributions are additive against the cohort baseline; they sum to the composite score and are recomputed whenever the underlying record changes.
Evidence
| District SoR benchmark | Rs 7.52 L |
| Peer cohort size | 91 works |
| Sanctioned | Rs 10.59 L |
| Released | Rs 10.80 L |
| Expenditure | Rs 13.29 L |
| Physical progress | 21% |
Record trail
- 14 Feb 2024Work sanctioned by the District Authority₹10.59 L · Gorakhpur Rural Engineering Service
- 14 Feb 2024First instalment released to the implementing agency₹5.40 L
- 15 Jan 2026D-02 fired during the nightly scoring runRobust z-score on peer cohort · confidence 0.89
- 15 Jan 2026Alert routed to Ministry review deskResponse window 15 days
The work
Detector
Unit rate above district schedule of rates
Per-unit cost of an asset sits in the upper tail of comparable works in the same district and quarter after size normalisation.