Payment burst concentrated in the closing weeks of the financial year
Check dam on nala · Coimbatore, Tamil Nadu · sanctioned 17 Sep 2025 · detected 24 Feb 2026 (51 days ago)
Why this was flagged
Point-process burst detection evaluated this work against 531 comparable sanctions in Tamil Nadu for the same category and financial year. Abnormal clustering of releases and bills into the closing weeks of the financial year relative to the work's own execution curve. The residual for this record falls outside the learned tolerance, and the contribution breakdown below isolates which measured features carried the score.
- 01Bill submission burst intensity+24.5
- 02Deviation from execution curve+15.9
- 03Share of releases in final 30 days+15.7
- 04Prior-year year-end pattern+11.2
- 05Sanction-to-payment latency+5.7
Contributions are additive against the cohort baseline; they sum to the composite score and are recomputed whenever the underlying record changes.
Evidence
| Releases in final 30 days | 68% |
| Bills submitted in week 52 | 17 |
| Sanctioned | Rs 29.51 L |
| Released | Rs 25.53 L |
| Expenditure | Rs 8.72 L |
| Physical progress | 100% |
Record trail
- 17 Sep 2025Work sanctioned by the District Authority₹29.51 L · Coimbatore Public Works Department
- 17 Sep 2025First instalment released to the implementing agency₹12.77 L
- 24 Feb 2026D-08 fired during the nightly scoring runPoint-process burst detection · confidence 0.94
- 24 Feb 2026Alert routed to District Collector cellResponse window 15 days
The work
Detector
Fiscal year-end payment burst
Abnormal clustering of releases and bills into the closing weeks of the financial year relative to the work's own execution curve.