CriticalUnder reviewD-08 · FinancialOwner: Ministry review desk

Payment burst concentrated in the closing weeks of the financial year

Hybrid mast at chowk · Palakkad, Kerala · sanctioned 13 Mar 2025 · detected 23 Mar 2026 (22 days ago)

Why this was flagged

score 92 / 100

Point-process burst detection evaluated this work against 739 comparable sanctions in Kerala for the same category and financial year. Abnormal clustering of releases and bills into the closing weeks of the financial year relative to the work's own execution curve. The residual for this record falls outside the learned tolerance, and the contribution breakdown below isolates which measured features carried the score.

Composite score
92
Model confidence
0.85
Peer cohort
720 works
Tier
Critical ≥ 82
Feature contribution to the score
  1. 01Share of releases in final 30 days+28.3
  2. 02Bill submission burst intensity+24.6
  3. 03Prior-year year-end pattern+15.1
  4. 04Deviation from execution curve+14.6
  5. 05Sanction-to-payment latency+9.3

Contributions are additive against the cohort baseline; they sum to the composite score and are recomputed whenever the underlying record changes.

Evidence

drawn from the source records
Releases in final 30 days72%
Bills submitted in week 5219
SanctionedRs 85.17 L
ReleasedRs 70.43 L
ExpenditureRs 29.58 L
Physical progress20%

Record trail

  1. 13 Mar 2025Work sanctioned by the District Authority₹85.17 L · Palakkad Municipal Corporation
  2. 13 Mar 2025First instalment released to the implementing agency₹35.22 L
  3. 23 Mar 2026D-08 fired during the nightly scoring runPoint-process burst detection · confidence 0.85
  4. 23 Mar 2026Alert routed to Ministry review deskResponse window 7 days

The work

MPLADS/KL/2550
Asset
Hybrid mast at chowk
Category
Solar street lighting
Recommended by
T. Mahato · Rajya Sabha
Constituency
Palakkad 3
Implementing agency
Palakkad Municipal Corporation
Contractor
Aravalli Civil Works
Status
Stalled
Beneficiaries
2,113
Money
Sanctioned85.17 L
Released70.43 L
Expenditure29.58 L
Unspent with agency40.85 L
Physical progress20%

Detector

D-08

Fiscal year-end payment burst

Abnormal clustering of releases and bills into the closing weeks of the financial year relative to the work's own execution curve.

Point-process burst detectionFinancial

Other flags on this work

2

Comparable detections

D-08