88% of released funds drawn at 8% physical progress
Field channel lining · Jalpaiguri, West Bengal · sanctioned 27 Jan 2024 · detected 02 Mar 2026 (1 days ago)
Why this was flagged
Isolation Forest on progress-payment gap evaluated this work against 211 comparable sanctions in West Bengal for the same category and financial year. Funds released and drawn while the geo-tagged photographic and measurement-book evidence shows no corresponding advance. The residual for this record falls outside the learned tolerance, and the contribution breakdown below isolates which measured features carried the score.
- 01Payment / progress divergence+31.1
- 02Days since last progress photo+26.3
- 03Third-party inspection lag+12.4
- 04Measurement-book gap+11.6
- 05Advance drawn as share of release+5.6
Contributions are additive against the cohort baseline; they sum to the composite score and are recomputed whenever the underlying record changes.
Evidence
| Last progress photo | 206 days ago |
| Measurement book entries | 2 |
| Sanctioned | Rs 33.20 L |
| Released | Rs 32.20 L |
| Expenditure | Rs 28.42 L |
| Physical progress | 8% |
Record trail
- 27 Jan 2024Work sanctioned by the District Authority₹33.20 L · Jalpaiguri Public Works Department
- 27 Jan 2024First instalment released to the implementing agency₹16.10 L
- 02 Mar 2026D-05 fired during the nightly scoring runIsolation Forest on progress-payment gap · confidence 0.86
- 02 Mar 2026Alert routed to State Nodal AuthorityResponse window 7 days
The work
Detector
Payment without physical progress
Funds released and drawn while the geo-tagged photographic and measurement-book evidence shows no corresponding advance.