88% of released funds drawn at 6% physical progress
Reading room fit-out · Nashik, Maharashtra · sanctioned 08 Jan 2024 · detected 08 Mar 2026 (7 days ago)
Why this was flagged
Isolation Forest on progress-payment gap evaluated this work against 650 comparable sanctions in Maharashtra for the same category and financial year. Funds released and drawn while the geo-tagged photographic and measurement-book evidence shows no corresponding advance. The residual for this record falls outside the learned tolerance, and the contribution breakdown below isolates which measured features carried the score.
- 01Payment / progress divergence+34.8
- 02Third-party inspection lag+20.9
- 03Days since last progress photo+17.2
- 04Measurement-book gap+15.1
- 05Advance drawn as share of release+11.0
Contributions are additive against the cohort baseline; they sum to the composite score and are recomputed whenever the underlying record changes.
Evidence
| Last progress photo | 107 days ago |
| Measurement book entries | 1 |
| Sanctioned | Rs 48.92 L |
| Released | Rs 45.67 L |
| Expenditure | Rs 40.07 L |
| Physical progress | 6% |
Record trail
- 08 Jan 2024Work sanctioned by the District Authority₹48.92 L · Nashik Zilla Parishad Works Division
- 08 Jan 2024First instalment released to the implementing agency₹22.84 L
- 08 Mar 2026D-05 fired during the nightly scoring runIsolation Forest on progress-payment gap · confidence 0.95
- 08 Mar 2026Alert routed to Ministry review deskResponse window 7 days
- 08 Mar 2026Escalated to the State Nodal AuthorityAwaiting agency reply
The work
Detector
Payment without physical progress
Funds released and drawn while the geo-tagged photographic and measurement-book evidence shows no corresponding advance.