← Alert queue/ALT-26-0103
CriticalEscalatedD-06 · ExecutionOwner: State Nodal Authority

Completion projected to slip past the sanctioned window

Reading room fit-out · Nashik, Maharashtra · sanctioned 08 Jan 2024 · detected 10 Jan 2026 (65 days ago)

Why this was flagged

score 92 / 100

Survival model + seasonal decomposition evaluated this work against 392 comparable sanctions in Maharashtra for the same category and financial year. A forward estimate of the completion date from progress velocity, monsoon seasonality and agency history flags works that will slip. The residual for this record falls outside the learned tolerance, and the contribution breakdown below isolates which measured features carried the score.

Composite score
92
Model confidence
0.77
Peer cohort
152 works
Tier
Critical ≥ 82
Feature contribution to the score
  1. 01Progress velocity (last 90 days)+31.2
  2. 02Monsoon exposure of remaining scope+25.5
  3. 03Agency completion-rate history+16.5
  4. 04Elapsed vs sanctioned duration+11.3
  5. 05Open work count with the agency+7.5

Contributions are additive against the cohort baseline; they sum to the composite score and are recomputed whenever the underlying record changes.

Evidence

drawn from the source records
Sanctioned window16 months
Projected completion+12 months
SanctionedRs 48.92 L
ReleasedRs 45.67 L
ExpenditureRs 40.07 L
Physical progress6%

Record trail

  1. 08 Jan 2024Work sanctioned by the District Authority₹48.92 L · Nashik Zilla Parishad Works Division
  2. 08 Jan 2024First instalment released to the implementing agency₹22.84 L
  3. 10 Jan 2026D-06 fired during the nightly scoring runSurvival model + seasonal decomposition · confidence 0.77
  4. 10 Jan 2026Alert routed to State Nodal AuthorityResponse window 7 days
  5. 10 Jan 2026Escalated to the State Nodal AuthorityAwaiting agency reply

The work

MPLADS/MH/2517
Asset
Reading room fit-out
Category
Public library & IT
Recommended by
U. Solanki · Rajya Sabha
Constituency
Nashik 4
Implementing agency
Nashik Zilla Parishad Works Division
Contractor
Kaveri Infrastructure
Status
Stalled
Beneficiaries
7,319
Money
Sanctioned48.92 L
Released45.67 L
Expenditure40.07 L
Unspent with agency5.60 L
Physical progress6%

Detector

D-06

Predicted completion overrun

A forward estimate of the completion date from progress velocity, monsoon seasonality and agency history flags works that will slip.

Survival model + seasonal decompositionExecution

Other flags on this work

2

Comparable detections

D-06