HighOpenD-06 · ExecutionOwner: District Collector cell

Completion projected to slip past the sanctioned window

Field channel lining · Jalpaiguri, West Bengal · sanctioned 27 Jan 2024 · detected 17 Feb 2026 (44 days ago)

Why this was flagged

score 78 / 100

Survival model + seasonal decomposition evaluated this work against 471 comparable sanctions in West Bengal for the same category and financial year. A forward estimate of the completion date from progress velocity, monsoon seasonality and agency history flags works that will slip. The residual for this record falls outside the learned tolerance, and the contribution breakdown below isolates which measured features carried the score.

Composite score
78
Model confidence
0.87
Peer cohort
883 works
Tier
High ≥ 66
Feature contribution to the score
  1. 01Monsoon exposure of remaining scope+24.6
  2. 02Progress velocity (last 90 days)+21.2
  3. 03Agency completion-rate history+15.8
  4. 04Elapsed vs sanctioned duration+9.0
  5. 05Open work count with the agency+7.4

Contributions are additive against the cohort baseline; they sum to the composite score and are recomputed whenever the underlying record changes.

Evidence

drawn from the source records
Sanctioned window12 months
Projected completion+13 months
SanctionedRs 33.20 L
ReleasedRs 32.20 L
ExpenditureRs 28.42 L
Physical progress8%

Record trail

  1. 27 Jan 2024Work sanctioned by the District Authority₹33.20 L · Jalpaiguri Public Works Department
  2. 27 Jan 2024First instalment released to the implementing agency₹16.10 L
  3. 17 Feb 2026D-06 fired during the nightly scoring runSurvival model + seasonal decomposition · confidence 0.87
  4. 17 Feb 2026Alert routed to District Collector cellResponse window 15 days

The work

MPLADS/WB/2483
Asset
Field channel lining
Category
Minor irrigation
Recommended by
U. Solanki · Lok Sabha
Constituency
Jalpaiguri 1
Implementing agency
Jalpaiguri Public Works Department
Contractor
Kaveri Infrastructure
Status
Sanctioned
Beneficiaries
20,079
Money
Sanctioned33.20 L
Released32.20 L
Expenditure28.42 L
Unspent with agency3.78 L
Physical progress8%

Detector

D-06

Predicted completion overrun

A forward estimate of the completion date from progress velocity, monsoon seasonality and agency history flags works that will slip.

Survival model + seasonal decompositionExecution

Other flags on this work

1

Comparable detections

D-06