Completion projected to slip past the sanctioned window
Solar street lights, 40 poles · Madurai, Tamil Nadu · sanctioned 06 Sep 2025 · detected 21 Feb 2026 (48 days ago)
Why this was flagged
Survival model + seasonal decomposition evaluated this work against 620 comparable sanctions in Tamil Nadu for the same category and financial year. A forward estimate of the completion date from progress velocity, monsoon seasonality and agency history flags works that will slip. The residual for this record falls outside the learned tolerance, and the contribution breakdown below isolates which measured features carried the score.
- 01Progress velocity (last 90 days)+25.6
- 02Monsoon exposure of remaining scope+19.7
- 03Agency completion-rate history+8.2
- 04Elapsed vs sanctioned duration+8.0
- 05Open work count with the agency+3.4
Contributions are additive against the cohort baseline; they sum to the composite score and are recomputed whenever the underlying record changes.
Evidence
| Sanctioned window | 18 months |
| Projected completion | +16 months |
| Sanctioned | Rs 15.96 L |
| Released | Rs 9.56 L |
| Expenditure | Rs 9.50 L |
| Physical progress | 55% |
Record trail
- 06 Sep 2025Work sanctioned by the District Authority₹15.96 L · Madurai Rural Engineering Service
- 06 Sep 2025First instalment released to the implementing agency₹4.78 L
- 21 Feb 2026D-06 fired during the nightly scoring runSurvival model + seasonal decomposition · confidence 0.82
- 21 Feb 2026Alert routed to Ministry review deskResponse window 30 days
- 21 Feb 2026Closed by the reviewing deskDisposal recorded as a training label
The work
Detector
Predicted completion overrun
A forward estimate of the completion date from progress velocity, monsoon seasonality and agency history flags works that will slip.