72% of released funds drawn at 9% physical progress
Station forecourt paving · Bardhaman, West Bengal · sanctioned 02 Oct 2025 · detected 02 Mar 2026 (1 days ago)
Why this was flagged
Isolation Forest on progress-payment gap evaluated this work against 547 comparable sanctions in West Bengal for the same category and financial year. Funds released and drawn while the geo-tagged photographic and measurement-book evidence shows no corresponding advance. The residual for this record falls outside the learned tolerance, and the contribution breakdown below isolates which measured features carried the score.
- 01Payment / progress divergence+26.6
- 02Days since last progress photo+22.4
- 03Measurement-book gap+12.3
- 04Third-party inspection lag+5.1
- 05Advance drawn as share of release+4.6
Contributions are additive against the cohort baseline; they sum to the composite score and are recomputed whenever the underlying record changes.
Evidence
| Last progress photo | 218 days ago |
| Measurement book entries | 1 |
| Sanctioned | Rs 142.97 L |
| Released | Rs 134.57 L |
| Expenditure | Rs 96.89 L |
| Physical progress | 9% |
Record trail
- 02 Oct 2025Work sanctioned by the District Authority₹1.43 Cr · Bardhaman District Rural Development Agency
- 02 Oct 2025First instalment released to the implementing agency₹67.28 L
- 02 Mar 2026D-05 fired during the nightly scoring runIsolation Forest on progress-payment gap · confidence 0.91
- 02 Mar 2026Alert routed to District Collector cellResponse window 15 days
The work
Detector
Payment without physical progress
Funds released and drawn while the geo-tagged photographic and measurement-book evidence shows no corresponding advance.