National · all states and union territories
Synthetic demo data
Overview
← Alert queue/ALT-26-0067
HighUnder reviewD-01 · FinancialOwner: State Nodal Authority

Expenditure exceeds sanctioned estimate by 43%

Multipurpose shelter · Bareilly, Uttar Pradesh · sanctioned 14 Jan 2026 · detected 26 Feb 2026 (53 days ago)

Why this was flagged

score 73 / 100

Gradient-boosted residuals evaluated this work against 208 comparable sanctions in Uttar Pradesh for the same category and financial year. Final expenditure diverges from the approved estimate beyond the tolerance learned for that work category, district and year. The residual for this record falls outside the learned tolerance, and the contribution breakdown below isolates which measured features carried the score.

Composite score
73
Model confidence
0.84
Peer cohort
912 works
Tier
High ≥ 66
Feature contribution to the score
  1. 01Category cost residual (district)+24.5
  2. 02Expenditure / sanction ratio+23.9
  3. 03Revised estimate count+12.9
  4. 04Time between revisions+8.4
  5. 05Agency historical overrun rate+3.4

Contributions are additive against the cohort baseline; they sum to the composite score and are recomputed whenever the underlying record changes.

Evidence

drawn from the source records
Category median (district)Rs 8.27 L
Revisions on record4
SanctionedRs 10.09 L
ReleasedRs 10.29 L
ExpenditureRs 14.47 L
Physical progress57%

Record trail

  1. 14 Jan 2026Work sanctioned by the District Authority₹10.09 L · Bareilly District Rural Development Agency
  2. 14 Jan 2026First instalment released to the implementing agency₹5.14 L
  3. 26 Feb 2026D-01 fired during the nightly scoring runGradient-boosted residuals · confidence 0.84
  4. 26 Feb 2026Alert routed to State Nodal AuthorityResponse window 15 days

The work

MPLADS/UP/2476
Asset
Multipurpose shelter
Category
Community hall / Anganwadi
Recommended by
P. Choudhury · Lok Sabha
Constituency
Bareilly 2
Implementing agency
Bareilly District Rural Development Agency
Contractor
Konark Buildcon
Status
In progress
Beneficiaries
12,702
Money
Sanctioned10.09 L
Released10.29 L
Expenditure14.47 L
Unspent with agency0.00 L
Physical progress57%

Detector

D-01

Cost overrun against sanctioned estimate

Final expenditure diverges from the approved estimate beyond the tolerance learned for that work category, district and year.

Gradient-boosted residualsFinancial

Other flags on this work

2

Comparable detections

D-01